GERMANTOWN CENTER.

RDS is handling the ground up development of the new Germantown Town Center East Phase. The project consists of about 40 acres of site work, all utility construction, road improvements, and building pad deliveries and sales. RDS has direct contractor responsibility, as field Project Manager for the out-of-state contractor, and dual accountability to the owner as their personal representative. Germantown Town Center is managed on a fast track system - all entitlements are tied to very specific contract performance dates. Currently, the project is on schedule, despite heavy Spring and Summer rains from 2000.

.

.

.

.

.

.

..

.

.

.

.

.